CITY OF SEATTLE
ORDINANCE __________________
COUNCIL BILL __________________
title
AN ORDINANCE relating to the Central Puget Sound Regional Transit Authority (“Sound Transit”); authorizing execution of the “Lynnwood Link Supplement to the Memorandum of Agreement for Intergovernmental Cooperation (April 20, 1998) between Central Puget Sound Regional Transit Authority (Sound Transit) and the City of Seattle for the Central Link Light Rail Project”; and ratifying and confirming certain prior acts.
body
WHEREAS, on April 20, 1998, pursuant to Ordinance 118927, the City executed a Memorandum of Agreement for Intergovernmental Cooperation with Sound Transit regarding Light Rail Development (“MOA”); and
WHEREAS, in response to Sound Transit’s request for continued City support for Link light rail projects in exchange for Sound Transit’s reimbursement of expenses incurred by the City in connection with such work, the MOA has been supplemented for the Central Link, University Link portion of the Central Link, Northgate Link, and East Link light rail projects; and
WHEREAS, Sound Transit has requested City support for design review, for expedited permitting and engineering services for the Lynnwood Link light rail extension project, and for limited ongoing program management services for the Lynnwood Link light rail extension project, and has agreed to reimburse the City for its expenses incurred in connection with such work; NOW, THEREFORE,
BE IT ORDAINED BY THE CITY OF SEATTLE AS FOLLOWS:
Section 1. As requested by the Director of Transportation and recommended by the Mayor, the Director of Transportation or the Director’s designee is hereby authorized to execute, for and on behalf of the City of Seattle, the “Lynnwood Link Supplement to the Memorandum of Agreement for Intergovernmental Cooperation (April 20, 1998) between Central Puget Sound Regional Transit Authority (Sound Transit) and the City of Seattle for the Central Link Light Rail Project”, substantially in the form of Attachment 1 to this ordinance, providing for Sound Transit reimbursement for City services provided in support of the Lynnwood Link light rail extension project.
Section 2. Any act consistent with the authority of this ordinance taken after its passage and prior to its effective date is ratified and confirmed.
Section 3. This ordinance shall take effect and be in force 30 days after its approval by the Mayor, but if not approved and returned by the Mayor within ten days after presentation, it shall take effect as provided by Seattle Municipal Code Section 1.04.020.
Passed by the City Council the ________ day of _________________________, 2016, and signed by me in open session in authentication of its passage this _____ day of _________________________, 2016.
____________________________________
President ____________ of the City Council
Approved by me this ________ day of _________________________, 2016.
____________________________________
Edward B. Murray, Mayor
Filed by me this ________ day of _________________________, 2016.
____________________________________
Monica Martinez Simmons, City Clerk
(Seal)
Attachments:
Attachment 1 - Lynnwood Link Supplement to the Memorandum of Agreement for Intergovernmental Cooperation (April 20, 1998) between Central Puget Sound Regional Transit Authority (Sound Transit) and the City of Seattle for the Central Link Light Rail Project
Exhibit A - Lynnwood Link Supplement Scope of Work
Exhibit B - Lynnwood Link Supplement Schedule
Exhibit C - Lynnwood Link Supplement Budget
Exhibit D - Lynnwood Link Supplement Federal Funding Requirements